| Who regulates | <cite index="9-3">DPH's Environmental Health section regulates on-site sewage management systems under Rules of the Georgia Department of Public Health, Chapter 511-3-1</cite>, and <cite index="9-5">159 county health departments act as the local permitting authority.</cite> | rules.sos.ga.gov |
| Permit required before work | <cite index="11-4">No one may begin physical development of a lot or structure that will use a septic system, or install a system or component, without first getting a construction permit from the County Health Department.</cite> | law.cornell.edu |
| Permit validity | <cite index="12-3">Construction permits remain valid for no more than twelve months from the date of issue.</cite> | rules.sos.ga.gov |
| Site/soil approval | <cite index="6-3">Permits are issued only after a County Board of Health site inspection shows favorable findings on absorption rates, soil, groundwater, rock and other factors.</cite> <cite index="38-8">Permits for conventional or chamber systems are denied where bedrock or other impervious strata are less than two feet below the bottom of the proposed absorption field.</cite> | dph.georgia.gov |
| Final inspection before backfill | <cite index="10-5">No person may backfill or use a septic system until a final inspection has been done.</cite> | dph.georgia.gov |
| Sewer connection | <cite index="13-6">Connection must be made to a public or community sewage treatment system if one is available within 200 feet of the property line</cite> (2014 county-adopted copy of the state rule). <cite index="12-1">A failing residential system under 2,000 gallons per day may be exempted from connecting to sewer if the repair or replacement meets Manual criteria and has sufficient area and usable soils.</cite> | cobbanddouglaspublichealth.com |
| Tank setbacks | <cite index="38-3">The March 2026 DPH manual says a septic tank may not be less than 50 ft from boreholes, lakes, ponds, streams, watercourses and other impoundments, less than 10 ft from pressure water supply lines, or less than 10 ft from a property line.</cite> An older DPH-rule copy listed <cite index="42-5">50 ft from wells/springs and 25 ft from lakes, ponds and streams</cite>, so confirm the current distance with your county office. | dph.georgia.gov |
| Absorption field setbacks | <cite index="38-6">An absorption field may not be built less than 100 ft from wells, and less than 5 ft from buildings without basements, other structures, drives, hardscape and property lines.</cite> The 100 ft figure is from the truncated manual text and is confirmed by the exam study guide. <cite index="41-9">The manual adds that where individual water supplies serve the properties, the field must be at least 50 ft from property lines.</cite> That last item comes from a contractor website summarizing the manual, not an official source. | dph.georgia.gov |
| Tank design | <cite index="5-3,5-4">An approved filter must be installed on the tank outlet, and tank capacity must be increased by 50% if a garbage grinder is used.</cite> | rules.sos.ga.gov |
| Pumping/septage removal | <cite index="5-5">No one may remove or dispose of septic tank contents without a septage removal permit issued by the County Board of Health.</cite> <cite index="5-6">The firm name and permit number must be lettered on both sides of each septage vehicle.</cite> | rules.sos.ga.gov |
| Pumping schedule | I found no official DPH source setting a mandatory pumping interval. A secondary source says <cite index="36-9">Georgia does not mandate a specific pumping schedule for homeowners</cite> and <cite index="36-11">cites the EPA recommendation of inspection every 1–3 years and pumping every 3–5 years.</cite> | septictankhub.com |
| Operation/additives | <cite index="10-8">No strong bases, acids or organic solvents may be used in the operation of a septic system.</cite> <cite index="6-9">Unapproved discharge or spillage of sewage is prohibited.</cite> | dph.georgia.gov |
| Inspection at property sale | I found no official state or county rule requiring a septic inspection at sale. Secondary sources say <cite index="32-5">Georgia has no statewide law requiring a septic inspection on property transfers</cite>, but <cite index="35-2">FHA, VA and most conventional lenders require proof of a functioning system.</cite> | septicandwell.com |
| Large systems | <cite index="11-9">If a proposed system will produce more than 2,000 gallons per day of sewage flow, plans, specifications, soil data and absorption test data must be submitted to the County Board of Health to obtain a construction permit.</cite> | law.cornell.edu |
| Approved tanks | <cite index="5-2">Anyone seeking approval of septic tanks for use in on-site systems must submit detailed plans and specifications for tank manufacture to the Department.</cite> I did not find a consolidated public list of approved tank models in these results. Ask DPH or your county environmental health office. | rules.sos.ga.gov |