| Who regulates | <cite index='1-1'>ADPH Chapter 420-3-1 (State Board of Health) sets requirements for the design, permitting, installation, approval and operation of onsite sewage systems.</cite> | alabamapublichealth.gov |
| Permit before work | <cite index='19-3'>Under rule 420-3-1-.06(1), no one may begin installing or repairing an onsite system or component until the responsible person has been issued a valid Permit to Install (Repair) by the local health department.</cite> | alabamasepticguide.net |
| Inspection and Approval for Use | <cite index='12-8,12-9'>The owner calls the health department before installation to schedule an inspection, and the health department issues an Approval for Use before the building can be occupied.</cite> | alabamapublichealth.gov |
| Inspection at sale | I found no official Alabama source requiring a septic inspection at property sale. One non-official real-estate source states that <cite index='14-4'>no Alabama law makes a seller inspect a septic tank before a sale</cite>, so confirm with the county health department. | thewilliamsgroupal.com |
| System records | <cite index='40-1,40-2'>Property owners or their agents (attorneys, real estate agents, septic repair companies, developers) can ask the local health department for septic tank information.</cite> <cite index='40-15'>The completed permit, called the Approval for Use, includes a diagram of the actual installation.</cite> | alabamapublichealth.gov |
| Tank specifications | <cite index='8-7'>Concrete tanks must be designed, constructed and tested to the current ASTM C1227 standard.</cite> <cite index='8-14'>Metal tanks, drums, barrels or pipes are prohibited as sewage tanks.</cite> | admincode.legislature.state.al.us |
| Approved (pre-made) tanks | <cite index='30-7'>No pre-made septic tank, grease trap or holding tank may be installed unless a permit has been issued for that tank series.</cite> <cite index='31-1'>ADPH Form CEP-11 is the application for that permit.</cite> | admincode.legislature.state.al.us |
| Setbacks | <cite index='38-1'>Minimum setbacks for drain fields, septic tanks, pump chambers and similar components are set out in Table 4 of Rule 420-3-1-.65.</cite> I could not retrieve the Table 4 figures from an official source. Secondary sites give conflicting distances, so none are reported here. Get the exact distances from your county health department. | regulations.justia.com |
| Effluent line crossings | <cite index='38-2'>An effluent line may cross a water line if 18 inches of vertical separation is kept, with the effluent line passing under the water line.</cite> | regulations.justia.com |
| Pumping and maintenance | I found no mandatory pumping interval in the sources. <cite index='43-13'>ADPH recommends pumping the tank every three to five years to prevent sludge build-up.</cite> <cite index='41-8'>Pumpers must hold an AOWB license to pump tanks and dispose of the septage in an approved manner.</cite> | alabamapublichealth.gov |
| Inspection frequency (recommended) | <cite index='41-3'>ADPH's homesite guide says the tank should be inspected once every two to three years.</cite> <cite index='46-14'>Its maintenance brochure advises contacting a licensed contractor for service every 1-2 years.</cite> Neither is a legal requirement. | alabamapublichealth.gov |
| Effluent filter | <cite index='46-2'>ADPH advises having an effluent filter placed in the septic tank.</cite> <cite index='28-7'>The installer's certification checklist includes an NSF Standard 46 effluent filter.</cite> | alabamapublichealth.gov |
| Flooding | <cite index='43-9,43-11'>Do not open the tank for pumping while the soil is still saturated, because a tank pumped in saturated soil may pop out of the ground.</cite> | alabamapublichealth.gov |
| Engineered systems and certifications | <cite index='6-5'>For an engineered system, the engineer certifies the design by signing ADPH Form CEP-2 or CEP-3.</cite> <cite index='23-14'>Before the Approval for Use is issued, the installer certifies the installation on ADPH Form CEP-5.</cite> | admincode.legislature.state.al.us |
| Abandonment | <cite index='30-10'>Rule 420-3-1-.24 requires an abandoned tank to be emptied and filled with sand or similar material, and its bottom may be ruptured.</cite> The exact fill material is cut off in the excerpt, so check the rule text. | admincode.legislature.state.al.us |